Hans Weemaes LEED AP · WELL AP
Insights / BD+C

LEED v5 Platinum: the four requirements on top of 80 points

Under v4, Platinum was a points total. Under v5 BD+C, a project can reach 80 points and still miss Platinum, because four credits carry minimum achievements.

The four requirements

CreditNew ConstructionCore and Shell
EAc1 Electrification5 points4 points
EAc3 Enhanced Energy Efficiency8 points5 points
EAc4 Renewable Energy100% of site energy use from Tier 1, 2 and 3 renewables100% of base building energy use from Tier 1, 2 and 3 renewables
MRc2 Reduce Embodied Carbon20% reduction20% reduction

Source: LEED v5 BD+C rating system, July 2026 edition, Appendix I.

What this means on a project

  • Decide on Platinum before schematic design. Electrification and embodied carbon are set by early system and structural choices. They are hard to recover late.
  • Core and Shell thresholds are lower but not trivial. 4 Electrification points and 5 efficiency points still rule out a conventional gas-fired base build.
  • Renewables must cover all of it. The requirement is 100% of energy use, from any mix of the three renewable tiers, not a share.
  • Points elsewhere can't compensate. A project short by one Electrification point is Gold, whatever its total.

Why it matters for the exam

This is exactly the kind of question a v4-trained candidate gets wrong: the arithmetic says Platinum, the rating system says Gold. Expect scenario questions that give you a points total and a credit breakdown, then ask for the certification level.